CONSTRUCTION UPDATE

  • The environmental impact assessment has been approved
  • Construction permit has already been issued
  • Structural work:
    • Foundation work 100% completed
    • 2nd basement slab 100% completed
    • 1st basement slab 100% completed
    • 1st floor slab 100% completed
    • 2nd floor slab 100% completed
    • 3rd floor slab 100% completed
    • 4th floor slab 100% completed
    • 5th floor slab 100% completed
    • 6th floor slab 100% completed
    • 7th floor slab 100% completed
    • 8th floor slab 100% completed
    • 9th floor slab 100% completed
    • 10th floor slab 100% completed
    • 11th floor slab 100% completed
    • 12th floor slab 100% completed
    • 14th floor slab 100% completed
    • 15th floor slab 100% completed
    • 16th floor slab 100% completed
    • 17th floor slab 100% completed
    • 17th floor roof slab 100% completed
    • Lift machine room 100% completed
  • MEP work:      
    • 2nd basement 78% completed
    • 1st basement 78% completed
    • 1st floor 85% completed
    • 2nd floor 65% completed
    • 3rd floor 95% completed
    • 4th floor 84% completed
    • 5th floor 90% completed
    • 6th floor 85% completed
    • 7th floor 81% completed
    • 8th floor 79% completed
    • 9th floor 66% completed
    • 10th floor 57% completed
    • 11th floor 45% completed
    • 12th floor 30% completed
    • 14th floor 24% completed
    • 15th floor 21% completed
    • 16th floor 18% completed
    • 17th floor 10% completed

    • Architectural work:
      • 2nd basement slab 90% completed
      • 1st basement slab 93% completed
      • 1st floor 60% completed
      • 2nd floor 50% completed
      • 3rd floor 70% completed
      • 4th floor 85% completed
      • 5th floor 77% completed
      • 6th floor 65% completed
      • 7th floor 75% completed
      • 8th floor 55% completed
      • 9th floor 47% completed
      • 10th floor 47% completed
      • 11th floor 42% completed
      • 12th floor 42% completed
      • 14th floor 33% completed
      • 15th floor 25% completed
      • 16th floor 25% completed
      • 17th floor 23% completed