CONSTRUCTION UPDATE

  • The environmental impact assessment has been approved
  • Construction permit has already been issued
  • Structural work:
    • Foundation work 100% completed
    • 2nd basement slab 100% completed
    • 1st basement slab 100% completed
    • 1st floor slab 100% completed
    • 2nd floor slab 100% completed
    • 3rd floor slab 100% completed
    • 4th floor slab 100% completed
    • 5th floor slab 100% completed
    • 6th floor slab 100% completed
    • 7th floor slab 100% completed
    • 8th floor slab 100% completed
    • 9th floor slab 100% completed
    • 10th floor slab 100% completed
    • 11th floor slab 100% completed
    • 12th floor slab 100% completed
    • 14th floor slab 100% completed
    • 15th floor slab 100% completed
    • 16th floor slab 100% completed
    • 17th floor slab 100% completed
    • 17th floor roof slab 100% completed
    • Lift machine room 100% completed
    • Top roof  floor slap 100% completed
  • MEP work:      
    • 2nd basement 96% completed
    • 1st basement 96% completed
    • 1st floor 88% completed
    • 2nd floor 88% completed
    • 3rd floor 95% completed
    • 4th floor 100% completed
    • 5th floor 100% completed
    • 6th floor 100% completed
    • 7th floor 100% completed
    • 8th floor 100% completed
    • 9th floor 100% completed
    • 10th floor 100% completed
    • 11th floor 100% completed
    • 12th floor 81% completed
    • 14th floor 74% completed
    • 15th floor 80% completed
    • 16th floor 78% completed
    • 17th floor 83% completed
    • Top roof floor 60% completed

    • Architectural work:
      • 2nd basement slab 98% completed
      • 1st basement slab 98% completed
      • 1st floor 80% completed
      • 2nd floor 65% completed
      • 3rd floor 82% completed
      • 4th floor 92% completed
      • 5th floor 93% completed
      • 6th floor 97% completed
      • 7th floor 98% completed
      • 8th floor 98% completed
      • 9th floor 75% completed
      • 10th floor 72% completed
      • 11th floor 80% completed
      • 12th floor 74% completed
      • 14th floor 72% completed
      • 15th floor 70% completed
      • 16th floor 70% completed
      • 17th floor 70% completed

    0 %

    OVERALL
    PROGRESS

    0 %

    STRUCTURAL
    WORKS

    0 %

    ARCHITECTURAL
    WORKS

    0 %

    LANDSCAPE
    WORKS

    0 %

    MEP
    WORKS

    0 %

    INTERIOR
    WORKS