CONSTRUCTION UPDATE

CONSTRUCTION UPDATE (PHASE 1)

NOVEMBER 2018

  • The environmental impact assessment has been approved
  • Construction permit has already been issued
  • Structural work:
    • Foundation work 96% completed
    • 2nd basement slab 60% completed
    • 1st basement slab 60% completed
    • 1st floor slab 60% completed
    • 2nd floor slab 60% completed
    • 3rd floor slab 10% completed
  • MEP work:      
    • 2nd basement slab 10% completed 