CONSTRUCTION UPDATE

CONSTRUCTION UPDATE (PHASE 1)

DECEMBER 2018

  • The environmental impact assessment has been approved
  • Construction permit has already been issued
  • Structural work:
    • Foundation work 99% completed
    • 2nd basement slab 93% completed
    • 1st basement slab 68% completed
    • 1st floor slab 60% completed
    • 2nd floor slab 60% completed
    • 3rd floor slab 60% completed
    • 4th floor slab 100% completed
    • 5th floor slab 67% completed
    • 6th floor slab 17% completed
  • MEP work:      
    • 2nd basement slab 50% completed
    • 1st basement slab 50% completed

    • Architectural work:
      • 2nd basement slab 40% completed
      • 1st basement slab 30% completed