CONSTRUCTION UPDATE

CONSTRUCTION UPDATE (PHASE 1)

JANUARY 2019

  • The environmental impact assessment has been approved
  • Construction permit has already been issued
  • Structural work:
    • Foundation work 100% completed
    • 2nd basement slab 100% completed
    • 1st basement slab 97% completed
    • 1st floor slab 70% completed
    • 2nd floor slab 60% completed
    • 3rd floor slab 60% completed
    • 4th floor slab 100% completed
    • 5th floor slab 100% completed
    • 6th floor slab 100% completed
    • 7th floor slab 100% completed
    • 8th floor slab 33% completed
  • MEP work:      
    • 2nd basement slab 60% completed
    • 1st basement slab 60% completed

    • Architectural work:
      • 2nd basement slab 80% completed
      • 1st basement slab 80% completed