CONSTRUCTION UPDATE

  • The environmental impact assessment has been approved
  • Construction permit has already been issued
  • Structural work:
    • Foundation work 100% completed
    • 2nd basement slab 100% completed
    • 1st basement slab 100% completed
    • 1st floor slab 98% completed
    • 2nd floor slab 100% completed
    • 3rd floor slab 90% completed
    • 4th floor slab 100% completed
    • 5th floor slab 100% completed
    • 6th floor slab 100% completed
    • 7th floor slab 100% completed
    • 8th floor slab 100% completed
    • 9th floor slab 100% completed
    • 10th floor slab 100% completed
    • 11th floor slab 100% completed
    • 12th floor slab 100% completed
    • 14th floor slab 100% completed
    • 15th floor slab 83% completed
    • 16th floor slab 33% completed
  • MEP work:      
    • 2nd basement 50% completed
    • 1st basement 50% completed
    • 1st floor 15% completed
    • 3rd floor 95% completed
    • 4th floor 10% completed
    • 5th floor 75% completed
    • 6th floor 40% completed
    • 7th floor 30% completed
    • 8th floor  30% completed

    • Architectural work:
      • 2nd basement slab 40% completed
      • 1st basement slab 40% completed
      • 1st floor 40% completed
      • 2nd floor 20% completed
      • 3rd floor 25% completed
      • 4th floor 25% completed
      • 5th floor 20% completed
      • 6th floor 17% completed
      • 7th floor 11% completed
      • 8th floor 5% completed
      • 9th floor 5% completed
      • 10th floor 5% completed