CONSTRUCTION UPDATE

  • The environmental impact assessment has been approved
  • Construction permit has already been issued
  • Structural work:
    • Foundation work 100% completed
    • 2nd basement slab 100% completed
    • 1st basement slab 100% completed
    • 1st floor slab 100% completed
    • 2nd floor slab 100% completed
    • 3rd floor slab 100% completed
    • 4th floor slab 100% completed
    • 5th floor slab 100% completed
    • 6th floor slab 100% completed
    • 7th floor slab 100% completed
    • 8th floor slab 100% completed
    • 9th floor slab 100% completed
    • 10th floor slab 100% completed
    • 11th floor slab 100% completed
    • 12th floor slab 100% completed
    • 14th floor slab 100% completed
    • 15th floor slab 100% completed
    • 16th floor slab 100% completed
    • 17th floor slab 100% completed
    • 17th floor roof slab 100% completed
    • Lift machine room 83% completed
  • MEP work:      
    • 2nd basement 78% completed
    • 1st basement 78% completed
    • 1st floor 85% completed
    • 2nd floor 65% completed
    • 3rd floor 95% completed
    • 4th floor 75% completed
    • 5th floor 90% completed
    • 6th floor 80% completed
    • 7th floor 75% completed
    • 8th floor 71% completed
    • 9th floor 55% completed
    • 10th floor 45% completed
    • 11th floor 32% completed
    • 12th floor 18% completed
    • 14th floor 14% completed
    • 15th floor 10% completed

    • Architectural work:
      • 2nd basement slab 67% completed
      • 1st basement slab 67% completed
      • 1st floor 47% completed
      • 2nd floor 32% completed
      • 3rd floor 62% completed
      • 4th floor 60% completed
      • 5th floor 55% completed
      • 6th floor 47% completed
      • 7th floor 42% completed
      • 8th floor 37% completed
      • 9th floor 30% completed
      • 10th floor 22% completed
      • 11th floor 17% completed
      • 12th floor 10% completed
      • 14th floor 7% completed
      • 15th floor 5% completed