CONSTRUCTION UPDATE

  • The environmental impact assessment has been approved
  • Construction permit has already been issued
  • Structural work:
    • Foundation work 100% completed
    • 2nd basement slab 100% completed
    • 1st basement slab 100% completed
    • 1st floor slab 100% completed
    • 2nd floor slab 100% completed
    • 3rd floor slab 100% completed
    • 4th floor slab 100% completed
    • 5th floor slab 100% completed
    • 6th floor slab 100% completed
    • 7th floor slab 100% completed
    • 8th floor slab 100% completed
    • 9th floor slab 100% completed
    • 10th floor slab 100% completed
    • 11th floor slab 100% completed
    • 12th floor slab 100% completed
    • 14th floor slab 100% completed
    • 15th floor slab 100% completed
    • 16th floor slab 100% completed
    • 17th floor slab 100% completed
    • 17th floor roof slab 100% completed
    • Lift machine room 100% completed
    • Top roof  floor slap 100% completed
  • MEP work:      
    • 2nd basement 99% completed
    • 1st basement 99% completed
    • 1st floor 95% completed
    • 2nd floor 95% completed
    • 3rd floor 95% completed
    • 4th floor 100% completed
    • 5th floor 100% completed
    • 6th floor 100% completed
    • 7th floor 100% completed
    • 8th floor 100% completed
    • 9th floor 100% completed
    • 10th floor 100% completed
    • 11th floor 100% completed
    • 12th floor 98% completed
    • 14th floor 97% completed
    • 15th floor 95% completed
    • 16th floor 95% completed
    • 17th floor 95% completed
    • Roof floor 75% completed
    • LMR floor 65% completed
    • Top Roof floor 65% completed
  • Landscape work:
    • 1st floor 30% completed
  • Interior work:
    • 1st floor 60% completed
    • 2nd floor 50% completed
    • 3rd floor 20% completed

    • Architectural work:
      • 2nd basement slab 99% completed
      • 1st basement slab 100% completed
      • 1st floor 89% completed
      • 2nd floor 88% completed
      • 3rd floor 87% completed
      • 4th floor 97% completed
      • 5th floor 96% completed
      • 6th floor 97% completed
      • 7th floor 98% completed
      • 8th floor 98% completed
      • 9th floor 85% completed
      • 10th floor 83% completed
      • 11th floor 80% completed
      • 12th floor 78% completed
      • 14th floor 77% completed
      • 15th floor 76% completed
      • 16th floor 77% completed
      • 17th floor 77% completed