- The environmental impact assessment has been approved
- Construction permit has already been issued
- Structural work:
- Foundation work 100% completed
- 2nd basement slab 100% completed
- 1st basement slab 100% completed
- 1st floor slab 100% completed
- 2nd floor slab 100% completed
- 3rd floor slab 100% completed
- 4th floor slab 100% completed
- 5th floor slab 100% completed
- 6th floor slab 100% completed
- 7th floor slab 100% completed
- 8th floor slab 100% completed
- 9th floor slab 100% completed
- 10th floor slab 100% completed
- 11th floor slab 100% completed
- 12th floor slab 100% completed
- 14th floor slab 100% completed
- 15th floor slab 100% completed
- 16th floor slab 100% completed
- 17th floor slab 100% completed
- 17th floor roof slab 100% completed
- Lift machine room 100% completed
- Top roof floor slap 100% completed
- MEP work:
- 2nd basement 99% completed
- 1st basement 99% completed
- 1st floor 95% completed
- 2nd floor 95% completed
- 3rd floor 95% completed
- 4th floor 100% completed
- 5th floor 100% completed
- 6th floor 100% completed
- 7th floor 100% completed
- 8th floor 100% completed
- 9th floor 100% completed
- 10th floor 100% completed
- 11th floor 100% completed
- 12th floor 98% completed
- 14th floor 97% completed
- 15th floor 95% completed
- 16th floor 95% completed
- 17th floor 95% completed
- Roof floor 75% completed
- LMR floor 65% completed
- Top Roof floor 65% completed
- Landscape work:
- 1st floor 30% completed
- Interior work:
- 1st floor 60% completed
- 2nd floor 50% completed
- 3rd floor 20% completed
- Architectural work:
- 2nd basement slab 99% completed
- 1st basement slab 100% completed
- 1st floor 89% completed
- 2nd floor 88% completed
- 3rd floor 87% completed
- 4th floor 97% completed
- 5th floor 96% completed
- 6th floor 97% completed
- 7th floor 98% completed
- 8th floor 98% completed
- 9th floor 85% completed
- 10th floor 83% completed
- 11th floor 80% completed
- 12th floor 78% completed
- 14th floor 77% completed
- 15th floor 76% completed
- 16th floor 77% completed
- 17th floor 77% completed